In my issue's list i cant see the current sprint in the column, it's displayed : "None [+1]" and if I expand [+1], i can see my current sprint. Thanks!
Hello @DANIEL Martin
Welcome to the Atlassian community.
Is that sprint a not yet started sprint (future sprint), a started sprint that has not yet been completed (active sprint), or a completed sprint?
The "+1" is usually an indication of sprints to which the issue was assigned where the sprint has already been set to Completed.
When the field shows "None" that is usually an indication that the issue is not currently assigned to a future or active sprint.
Did my response address your question? If so, please consider clicking on the Accept Answer button to mark your Question as Solved.