Unfortunatly i have closed the sprint before the deadline. is there way to open again?
Hi @Ramesh Krishnan
You can find the documentation here, but this can only be done if the project used is a Company managed project.
https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/
Hello Ramesh,
Welcome to community
Please try
To reopen a sprint:
If not already there, navigate to your project.
From your project’s sidebar, select Reports.
If you’re using a company-managed project, select the Sprint Report. If you’re using a team-managed project, select either the Burnup report or the Sprint burndown chart.
Select the relevant sprint from the sprint drop-down.
Select more (…) > Reopen sprint.
Select Reopen.
Thank you ,
Prachi