Hi Team,
I have a automation in place such that when a new issue type = story is created, 6 sub-tasks are created via automation for that specific story.
Now when the user adds original estimate value for the first time then the value for original estimate in the parent story reflects correctly. Below is the automation rule for my project:
Problem comes when the estimate is revised for any of the sub-tasks. The revised estimate doesn't get updated in the sub-task as well as parent story.