Challenge:
When projects start to fall behind due to us "building the plane while it's flying" there are Story tickets frequently pulled in that haven't been pointed.
Question:
Is there any way to require the Story Points field be filled out before a ticket status can move out of To-Do or be added to a Sprint?
Related:
I have automations to catch these, but they have to be triggered by the status change or the adding to a sprint. Neither are stopping someone really from just starting work on it and feigning ignorance that Jira rolled the Story back.