Im looking for some help / a plugin..
I currently have multiple development teams. Each team is made up of 3 - 5 Resources.
Each Team can we working across multiple projects at a time.
I want to be able to resource at a project / Team level.
what i want to do.
1) per member of the team i can allocate their hours per day ( availability or leave etc )
2) have a combined sum of all the people in the team per day/week/sprint ( configurable view )
3) Create the concept of a Project which has a time span of say 12 weeks.. ( i might have multiple projects defined and they can over lap each other )
4) have the tool determine where i will have resource clashed between projects. eg i might allocate that the team should work on project 100 for the first 3 weeks, then 50% for the next 3 , then 25% etc.. i want to be able to do this for each project.
As i allocate projects to a team it should ideally highlight when i have over resourced and allow me to juggle the project allocation.
I see so many tools that a focused on the story/person level, but i really dont care about the individuals i care about the team as a whole ( promoting team collaboration and swarming ) .. How each person is allocated to work in the team is irrelevant to me ( in general ) as they all have similar skills . I do want to know when im overloading a team with too many in parallel projects, so that i can shift durations or timelines. If the tool could work out the best project distribution to meet the time frames based on project size ( hours ) and team Capacity ( hours ) that would be a bonus.
Any tools in jira or not that meet this need?