Is there a way to configure Jira Plans to spread the workload evenly over the task duration instead of frontloading it? For example, if a task lasts 3 weeks with a total estimate of 30 hours, it should allocate 2 hours per day instead of scheduling everything at the beginning. Are there settings or workarounds to achieve this?
In Jira Plans, the workload for tasks is frontloaded, meaning that the total estimated time (Original Estimate) is scheduled as early as possible instead of being evenly distributed over the task duration. This results in an inaccurate capacity view, especially for long-running tasks.