Hi,
I have created custom statuses for my Software Team, like Code Review, Acceptance, Test Env, etc. All these custom statuses are assigned to 'Done' status as per our internal workflow.
Now when we complete one sprint, we want to also move issues with the custom statuses to the next sprint. This is because although they are assigned to 'Done', we need the issues to reach the final status of 'Done'.
However, Jira only allows the open issues to be moved to the next sprint. Since the custom statuses are assigned to 'Done', Jira considers them part of the Done column in the board. For analysis and reporting purposes, we would like to have the custom statuses to remain in the 'Done' column.
So is there a way to create a setting where I can move all issues to the next sprint, i.e all issues without the final 'Done' status?
Thanks!