When an issue that blocks another issue is delayed, I would like the dependent issue to also sync with this delay. E.g. If increase the due date of one issue by 2 weeks this triggers the due date AND start date for blocked issues to increase by 2 weeks.
I have been trying to create an automation for this, but it seems my smart values for start date are not functioning. However the due date smart values seem to function as desired.
I am using the following set up:
Trigger: When value changes for "Due date"
For Each: linked issue (blocks)
Action: Then edit issue field "due date" to
{{dueDate.plusDays(fieldChange.from.toDate.diff(fieldChange.to.toDate).days)}}
and "start date" to
{{startDate.plusDays(fieldChange.from.toDate.diff(fieldChange.to.toDate).days)}}
As described the due date functions corrects but the start date is removed altogether and left blank.
Any advice?