We plan large amounts of work in excel and then import them into Jira periodically. We tend to run our estimates in 0.5d, 1d, 1.5d etc.
Our issue is that whenever we import tasks that have .5 in the estimates, Jira is converting that into .43 somehwat inexplicably. A few data points to raise:
- We operate on 7 hour work days, so 0.5d is equal to 3.5 hours or 25200 seconds
- The math we are doing is d*25200 = estimate in seconds
- We import the estimates in seconds
- On the sheet, 0.5d is shown as 12600 seconds (or 3.5 hours)
- When imported, Jira changes this to 0.43d and when reviewing the XML output, the estimate is forced to 10800 seconds (or 3 hours)
My question is - why is Jira forcing the estimate of half a day down to 3 hours and not 3.5 hours when the working hours is 7, not 6? This has been driving us insane for weeks, any help is most welcome!