Hi,
I have an automation rule to change the status to Open when a backlog item is pulled into a sprint. What I have observed is that the rule is changing status to Open for an In Progress item when Sprint change happens. If I turn the automation rule off and changes Sprint for an In Progress item, status does not change and stays as In Progress.
Below is the automation rule I have. What is wrong here?