My engineering department is comprised of multiple teams. We use a single Jira project but all the engineering teams have their own board. We all organize on the same sprint cadence, so sprints are created that all teams use.
It seems that although the backlog view for my team's board in Jira shows these sprints, the timeline will not show the sprints at all. The only place it will show is if I go to the board that is basically the default board for whole project. No one uses this because it includes all issues for 10 teams.
I've seen some posts online that say that the Timeline will only show sprints created from that board. However, this makes little sense to me since stories can be assigned to any sprint within the project, regardless of where it was created. Similarly, all other views within my board show those sprints, so it seems internally inconsistent.
Is there any way to resolve this? It seems like a huge design flaw that severely takes away from value of the Timelines feature (which otherwise, is amazing).