Hi Everyone,
Currently we use Asana and we have 20 separate projects. We'd like to move into Agile (Scrum) and use JIRA. I'm not sure if we have the Premium version of JIRA or not.
We'll create 4 Scrum teams to look after specific projects. For instance;
- Team A - Project 1, Project 2
- Team B - Project 3, Project 4, Project 5
When we migrate our projects from Asana to JIRA, what would be the best configuration to accommodate this structure in Scrum?
Some alternatives came to my mind are:
1. Each project in Asana can become an Epic in JIRA. We can use the term Project in JIRA to collate each Team's works. We can distinguish projects through Epics on the Scrum board.
- Asana Team Name --> JIRA Project
- Asana Project --> JIRA Epic (Epics are tracked in Project)
2. If we migrate each project from Asana to JIRA - I mean each project can become a Project in JIRA as well. Is there any way to build a collateral Scrum view for each team? I heard of Plans, Top Level Planning, Cross Team Planning, which are confusing to me - can we use one of them to have a Scrum view?
Thanks.