Dear community,
I am wondering if it is possible to calculate an end date based on original estimates using the Jira App Big Gantt.
I am using dependencies "end-to-start" between task SCRUM-23 and SCRUM-24. The successor task always starts the day after the predecessor finishes. But the workload of task SCRUM-23 and SCRUM-24 is less than 8 hours, which means the tasks could be finished both on Dec 16th. I'm using the ASAP option within the dependencies as well.

Any suggestions how to fix that?
Thank you in advance!