I am on a project with friends, where I had hoped to use JIRA's etimates and logging to figure out how good we are at estimating and how lokng we spent on those tasks. We hope to scale this project eventually to full time if we get funding, and to craft a budget, we're figuring out these details.
But the thing is JIRA assumes we're working 40 hours work weeks. So if my colleague estimates 40 hours, takes 38, but across 2 weeks of his free time, then JIRA forces him to add a start date, which massively inflates his hours.
In fact, a 40 hour estimate gets immediatly converted to 1 week. I thought about disabling time tracking, but found no way to do so. I was hoping to use JIRA to get more robust info than Trello but maybe it's just not "personal project" friendly.