Hi,
I want to make the following selection:
all issues that changed to status completed during the last cw (14.-20 Sept. 2024) and that are actually in status completed (to avoid to show those that changed to completed at a point in time and than changed to another status again)
I use this jql:
project = P0ZEAE AND type IN ("Task KATB", "Sub-task KATB") AND status CHANGED TO "completed" During (startOfWeek(-1), endOfWeek(-1)) AND status = Completed
But the selection also shows issues with update date 21. Sept 2024.
Why is that? What is wrong with this jql?
Thank you very much for feedback!