Hello,
I'm hoping someone can help provide some guidance. I am new to Jira and automation.
I am attempting to build out a process flow for a new board.
I am creating a series of sub-tasks when the Parent Story/Bug is added to a sprint: DEV, Code Review, QA, UAT, Deploy, Validation.
I want to automate moving the sub-tasks to the appropriate status when the previous task is completed.
I've created the following rule:
When the DEV sub-task is transitioned to "Done" > Update the Parent to "Code Review." Then update the "Code Review" sub-task to Code Review as well.
The first step is working, the parent is moving to Code Review after the "Dev" sub-task is moved to done. The Code Review sub-task however is not updating.
Any guidance or tips would be greatly appreciated!