Have some ticket it status = "Done" but after closed sprint it effect have some ticket automatic moved to next sprint. How to resolve it ?Refer. Sprint 5 :
How to resolve it ?Refer. this url issue : https://lightnet-thailand.atlassian.net/jira/software/c/projects/NPI/boards/233/timeline
Hi @Yotawat Poboonwong
On you sprint board are all "Done" statuses related to the last column in the board.
This needs to be the case to have stated as closed in the sprint.
@Marc -Devoteam- Do you have example case that ? Please show me ? I need to see it, step by step.
You have a sprint board correct?
The sprint board has columns and in the columns you have specified a workflow status or statuses.
An issue is only considered "Done" in a sprint as all of the green "Done" state or states are in the last column of the board.
Otherwise issues are not considered "Done" in the sprint and will be transferred to the next
@Marc -Devoteam- You can do it show me by picture ?
It looks like you're new here. Sign in or register to get started.