Hello! I am completing a sprint, but for some reason all tasks with the Done and Reject status are being transferred to a new sprint, how can I fix this and what is the reason for this?
P.S Jira Cloud
Hi @Andrey Ivanov
What is your board column customization?
Hello!
Your Rejected status is unmapped, it needs to be part of the Done column.
Thank you very much, try it