When I started using the Plan functionality, specifically the Sprint Capacity Management view of the Plan shown below, my sprint dates were overlapping. As a result, there is a lot of white space underneath my Delivery Team row which should not be there. All the sprints should be on one row only (Row A). To achieve this, I need to change the historical sprint dates so that they are not overlapping (only those in the blue block, all subsequent dates are fine). How do I do this? Many thanks! Carol