Hi,
I have read some posts of people asking the same functionality but I want to be sure I didn't miss something to solve this, I explain.
I am working on chronologie to plan my project. I have a list of tasks, one after the other with estimated work time in days. But the calendar displays the weekends and we are not working these days.
Therefore, this is VERY inconvenient because I have to change all my tasks estimation to bypass the weekends. I could imagine doing that but the bigger problem is that if I want to reschedule my tasks, I need to change again the estimations of EVERY task moved according if it is now scheduled on a weekend or not...
Actually, if I can't delete weekends from chronologie, I don't know how people can use this.. I am missing something to work correctly with chronologie?