When I close a sprint and begin a New Sprint, the sprint number does not advance and I have to update it manually. This begin when we moved to cloud. What is the solution?
Ensure that your board settings are configured correctly:
Navigate to Board Settings:
Board settings
Check Sprint Field Configuration:
If you have automation rules set up for sprint creation or closing, ensure they are working correctly:
Go to Project Settings:
Project settings
Automation
Check Existing Rules:
While not ideal, manually updating the sprint number can be a temporary solution:
Close the Current Sprint:
Active sprints
Start a New Sprint:
Create Sprint
Sometimes, issues like this can be related to known bugs or changes in Jira Cloud:
Visit Atlassian Community:
Contact Atlassian Support:
If automatic sprint number advancement is crucial, consider using a custom field for sprint numbers and manage it through automation:
Create a Custom Field:
Jira settings
Issues
Custom fields
Configure Automation:
It looks like you're new here. Sign in or register to get started.