We are trying to create a global automation for all the projects in our Plan to populate the "target start" field with the start date of the sprint the ticket is in.
We created the global automation, but instead of populating the start of the sprint, it would populate today's date instead of the start date of the sprint.


--
This is secondary to my main question above, but I'm thinking about the whole concept of populating date fields and I'm curious of other people's thoughts. In a hardware and software development company, what is the optimal way to plan work and obtain dates while remaining agile? We need to do things like my question above and have dates and plan ahead, but how do we date our initiatives without turning too waterfall?