Hi Team, Is there a way in Jira Structure Gantt + resource view, to show how much a task was estimated and how much effort actually logged by assignee.
Example:
Current Date: 30Aug2024, UserStory_001 - Estimated 5 days, with start date as 1-Sep-2024
Current Date: 03Sep2024, UserStory_001 - User logged total 3 days effort (1 day effort daily from 1sep to 3rd sep, so total logged effort shown in jira is 3 days)
In this case, is there a possibility to show in Gantt view , how much effort was logged against the estimated period
Also in Resource usage view, can we get view of how much effort was planned on particular day for a resource and how much effort was logged by them