Hello community,
About closing epics when child issues are closed, what branch rule can cover "both" Epic->story and also Epic->sub task?
This rule works if stories (or bugs) are 'completed':

And this works for closing an epic when the child issue is a sub task:

These are two different branch rules, 1) For Epic (parent) and 2) For Parent.
Though how can an Epic with, for example, 1 story child and 1 sub-task be closed? (where the sub task is directly of the epic, not of the story)
- The 'For Epic (parent)' branch does not seem to recognize sub tasks as a direct child type.
The desired result is epic is transitioned to complete, when either the story or the sub task is transitioned to complete.
Thank you,
Chris