Hello,
I have a user who is trying to hide that they didn't complete a story at the end of the sprint. In the hour before sprint review they will move all their stories into the next sprint that they didn't finish. If the team calls them out, they become hostile and defensive.
There are times when a team must move a story out and into the backlog, but the closer to the end of a sprint, as Mike Cohn says, it becomes "game-ey" to hide that a story did not close and deprive the team from learning how to plan better next time.
Is there a permission an admin could use to prevent a user from moving a story from one sprint to another, at least for an hour? (lol)
Thanks