We run a lot of projects through a very repetitive process, so we set up a template epic that has a series of issues that align with all the tasks required to complete the project.
I'd like to set up an automation to copy dates from fields on specific child issues to fields on the parent epic. Does anyone know if this is possible?
For example, our Epics have a Content Development Phase that has 4 tasks, represented by child issues:
- Draft Write (This is the start of the writing phase. It automatically captures start and end dates of the task in fields on the issue when the issue moves to In Progress and Done.)
- SME Review
- SME Review Changes
- Build Course (This is the end of the writing phase. It automatically captures start and end dates of the task in fields on the issue when the issue moves to In Progress and Done.)
I'd like to automate copying dates from the child issues to the parent epic:
Draft Write Start Date (on child) = Content Development Phase Start (on parent)
Build Course End Date (on child) = Content Development Phase End (on parent)