Hello
When I open plans and auto-schedule the system proposes sprints and also sets the dates based on the sprints.
However, when I change the sprint in the backlog or in the plan then the dates do not update and therfeore the start and due date do not align with the newly selected sprint.
To correct it I need to remove the dates in which case the system uses the inferred sprint dates.
Anyone come across this?