I created a JQL but it seems that there is something wrong. Some issues that are not worked on for today's date are still appearing. This is in Team Board - Timeline.
Hi @Fritzie Quizon
Could you provide the JQL and an explanation of your expectations on what it should display?
Here is the JQL
It should only display all the work done in today's date. As you can see on the image i provided above, it still shows other dates like July 12,15 and Aug 5.
I would shorten the query for the update to:
updated >= 2024-08-07 (instead of updated >= "2024-08-06" AND updated <= "2024-08-07"), so this way you guarantee to get the results form today only.
However, your screenshot shows Start and End date which has not been filtered in your JQL and this is where you can get confused or thinking the JQL is not working as expected. You filter by updated date but not by Start or End dat so so display as they are 3 different fields.
You should think how would you like to filter this part, Start date, Due date or both.
If you are filtering using both dates, you can use the below after the assignee string:
"Start" >= "2024-08-07" and "End" >= "2024-08-07"
This will provide issues with a start date and end date for today, both included (note the name of field may be different)
I will try this. Thank you!