https://community.atlassian.com/t5/Jira-questions/Re-Change-the-due-date-of-all-tasks-and-subtasks-of-the/qaq-p/2381644/comment-id/634687#M634687
Hi there, this automation does what I want it to do, however the subtask is getting the old due date from the parent. Here is my scenario:
The user is updating a field (Network Type) in the parent to one of 3 values (Simple, Standard, Complex). The automation will kick in and change the due date on the parent as follows:
Simple = {{issue.created.plusBusinessDays(20)}}
Standard = {{issue.created.plusBusinessDays(20)}}
Complex = {{issue.created.plusBusinessDays(60)}}
This part of the automation works great
When the automation branches to the subtasks I set the subtask due date to {{triggerIssue.duedate}}
Unfortunately, the subtask due date is set to the original parent due date, not the updated date.