How can I create manageable milestones for my project for tracking at the Leadership level. Need milestones to publish to Leadership for management and tracking purposes.
There is a new Atlassian feature in beta called goals which might be the thing you are looking for. We are piloting that feature right now.
Another solution would be to have a dedicated page for each milestone and use the combination of page property and page property report where the milestone page contains a page property table with fields like name of the milestone, date of the milestone and status (on track or not).
Finally, another option is to have a specific Jira project for the milestones where you can maintain the status tracking at that specific Jira issue.
Thank you @Benjamin Jurg for your answer. Would there be a video which I can refer to for using this approach as it would be easier to try.
Which of the options are you most interested in?
Here my 2 cents considering the options:
Goals:
+ Dedicated for this purpose.
- New/beta thus unproven and has some beta-bugs.
Confluence pages:
+ Allows free format adding specific details to each milestone.
- Status tracking of the milestones is all manual.
Jira project:
+ Allows advanced status tracking.
- Adding more details is not that comfortable.
Depending on the organization style (some companies are very strongly Jira oriented, others more confluence oriented) that could influence the decision making too.
@Benjamin Jurg The approach: "Another solution would be to have a dedicated page for each milestone and use the combination of page property and page property report where the milestone page contains a page property table with fields like name of the milestone, date of the milestone and status (on track or not)." sounds good and I was looking for more insight to follow this approach.