From what i have found there is no automatic method for a sub-task start and end date to change automatically if the end date of a parent task changes. Do i really need to create automations for something this simple? I am trying to change over from MS Planner where i can move a task forward on the timeline and the sub-tasks automatically adjust. Without this very basic function, this will be a hard-sell in my organization. Am I missing something?