I have an automation that is manually triggered at Epic level.
The automation will create a number of task under that epic that it was triggered from.
However there is 1 task that needs to be created an assigned to a set epic in a different project.
For that task I have selected the Project I wish for it to be assigned too. But how do I put it under a designated Epic and have a link to the Epic that the automation has been triggered from.
Thanks,
Lou