I need create an automation that will copy Remaining Estimate's value into "Original Estimate" Field (Epic Sum Up type)
Could you please help me with this?
Thank you in advance!
Hello @Demo Test
Welcome to the Atlassian community.
Can you explain to us the problem you are trying to solve by overwriting an Original Estimate with Remaining Estimate?
If you do this you will not be able to report on how much progress has been made in comparison to the original estimate.
Hello @Trudy P Claspill
Thank you for your reply.
Please find attached the automation that gives error :
Is the Original Estimate field on the View/edit screen for the issue that triggered; the "Other requests" type issue?
Yes, it is on the View/edit screen