Story Points is a number field, associated to the correct Project and screens - is also searchable.
But when I try to add it to the Plan - I cannot find it.
Any help is appreciated
@hpatani
To show Story Points field in your 'Plans' you need to change your Estimation in Plans Settings. Go to Plans Settings > Scheduling > In Estimation change to Story points.
Then back to your plans and Story Points field should be displayed.
Thank you Fernando.
Hi @hpatani,
After changing the estimation method in your plan to Story points (as mentioned by @Fernando Eugênio da Silva, Jira's system field Story Points should become available under Fields in your timeline view, as well as Progress (story points). No additional import should be necessary.
If the story points field is a custom field you created yourself, apart from Jira's system field, it may well be that importing that field is not supported. In that case, I would recommend switching to the system field instead, since it is embedded in a lot of standard functionality in Jira out of the box.
Hope this helps!
That with @Fernando Eugênio da Silva response is very helpful.
will try your suggestions. Thank you!