In my Epic, the Child Issues section is reporting that every child issue is marked as "Closed" and the progress bar reports it as 100% done. However, when I go to my Epic Burndown report for the Epic, it reports 6 points as "Work Remaining" in the sprint.
Some additional details, the epic has had different portions pulled into various sprints across a few separate teams.
How are these points determined, and what troubleshooting options do I have to close out the Epic cleanly?