Hello Community,
I'm wondering if it's feasible to configure the "Sprint report" gadget to utilize the Sum of Original Estimates (the total of sub-task original estimates) instead of the Original Estimate value.
Hi @Lilit Tsaturyan,
Unfortunately this is not possible with the Jira's Sprint reports or its gadgets.
But a good solution for you would be the Sprint Burndown Burnup Chart gadget offered by our Great Gadgets app, which has an option to include the sub-tasks in the calculation. So it can display the sprint burndown/burnup by Original Estimate by counting all the issues from the sprint (tasks, stories and sub-tasks).
In addition, is displays a Data tab with a detailed sprint report, which displays also the sub-tasks and their estimate.
See also this article: https://community.atlassian.com/t5/App-Central/Tracking-an-agile-project-that-uses-time-estimates-with-Great/ba-p/1699994
To try this solution, you could start with a 1-month of free trial. If you have any questions, feel free to contact us at support@stonikbyte.com.
Hope this helps.
Danut.
Hi, @Lilit Tsaturyan!
With Agile Reports and Gadgets app, you can select what type of tasks you want to count, when using Time Tracking fields:
The Velocity chart can say you about given sprint more then only scope change and completed metrics:You can try it for free here. Hope, you find it helpful.Vasyl
@Danut M _StonikByte_
Thanks a lot.
One more question, Does that gadget show scope changes (added and removed tickets)?
Yes, it does.
Thank you