I am trying to change the End Date using an automation starting from an existing field (set as Number instead of day).
I read that you should set the Number in Days in order to be calculated but it does not work.
i did 1 automation which are applied in 2 different transition in the workflow.
In the first automation which is working, I extracted the Number of days (Duration) ==>customfield in Number)
between the planned and the start date.
Now,
I want , with the 2nd automation, add this number to the end date starting from the previous value already set Planned END date.
The automation should be as follow :
When Value changes for StartDate
then
Edit Issues field : End Date as follows
{{issue.Planned END Date.plusDays(issue.Duration.asDays)}}