Background: We have 2 boards under 1 project (Dev - Scrum and QA - Kanban).
Dev board Workflow: To Do, QA Failed, In Progress, Blocked, In Review, Dev Complete, Done.
QA board workflow: Dev Complete, QA Ready, QA In Progress, QA Blocked, QA Failed, Done
Problem: when transitioning tickets from Dev Board to QA Board ( status Dev Complete to QA Ready), it got reflected as burndown. The issue is that testing supposed to happen to reach Done status and only then it should reflect on Burndown chart.
Can you guys help how to fix it so that Burndown chart would show progress only when the status Done reached.