I have created the fields for my Automation project.
- Remaining Test Hours
- Shipping Time
- Tool Status
Remaining Test Hours: {{issue.subtasks."Test Hours".sum}} - computes the remaing test hours from all the subtasks assigned to the issue.
Shipping Time: {{"Need By Date".diff(now).hours.abs}} - calculates the time remaining hours left before shipment.
For the Tool Status: I have 3 predetermined values:
- On Track - Remaining Test Hours < Shipping Time by a wide margin
- At Risk - Remaining Test Hours < Shipping Time by 25%
- Delayed - Remaining Test Hours > Shipping Time
I just need a guide where to start and what is the best options i can do.