Is there a way to write a query to show all epics which previously had a due date of the current quarter and have been moved to a future quarter?
Hi Katherine - Welcome to the Atlassian Community!
You would need to create a custom Date field to capture the original Epic due date and populate it when you create the issue to be able to compare to the current Due date.
Hi @Katherine Gallagher
Natively, history searches (which look for previous field values) are only available for a small number of fields - Assignee, Reporter, Fix Version, Priority, Resolution, and Status.
For Due Dates, your options are...
Ste
Welcome to the community !!
As an alternative , you can try out our add-on for better reporting capabilities and viewing multiple issues history at once,
Issue History Reports
You can view the complete change log for your filtered issues, including changes to dates. Also this report can be exported to a csv file.
Disclaimer : I am part of the team which developed this app