Hi All
I have created an automation which calculates the difference in days between the baseline Date and Due Date when a project milestone due date is moved.
i have used the following inthe automation step
{{issue.Due date.diff(Baseline End Date).days}}
This outputs into a custom field with a number - however this only calculate the total days difference not the working days
Can anyone tell me how to create or amend the automation script to calculate as working days ?
regards
Rakesh