Hi,
I am looking for a way to unlink the completed sprints for these Jira tickets.
Please help
Hello @Swetha Kuruvatti
One way is to go through the bulk update route and clear Sprint values.
https://community.atlassian.com/t5/Jira-Software-questions/Bulk-Update-Delete-Sprint/qaq-p/595156
I tired bulk edit but it's not removing these values.
As I also did the move across different project, it's retaining all the old values from old project.
Hello,
Have you checked the box where it says "Change Sprint" and left the field blank? Cause I just tested and it wiped all values, even if the sprint was from a different board.
yes worked now! thank you.