I am a project manager and I use a Kanban board for our daily meetings for keeping track of resource tasks.
I want to convert this board to use it with sprints and then get reporting.
I am hitting a wall because all my resources are in a variety of different projects. The Jira out of the box reporting is hard to use as my Kanban board has a variety of projects in them.
The reporting I want to get is a burn down chart for each resource showing how much
- shows total of hours assigned by person, and a countdown on what is left. (Completed 26 out of 80 hrs). Burndown report.
- Need a report to show estimate vs actual by task, that can roll up by person, and by project
Has anyone done this? Are there plug ins that can help. Looking for some guidance