I have enabled child-level issue scheduling on timelines and set due dates for all issues but I am still unable to see issues other than epics on my timeline.
Hello, Good day. Parent issue should be on Epic issue type level, then the issue will be shown on Timeline. Please check the requirement : https://support.atlassian.com/jira-software-cloud/docs/set-up-the-roadmap/
All the issues are child issues on my epic.
Hi @Aaryan Bansal and welcome to the Community!
Navigate to your board settings / timeline and make sure you enable the child level issue scheduling option. After that, you should be able to add timeline bars to these child issues as well.
Hope this helps!