Documentation says:
"
You can track the progress of issues in your Jira application directly from your plan in Advanced Roadmaps.
When you connect a plan with your boards and projects, Advanced Roadmaps can detect the estimation unit of these issues, with the following conditions to note:
- If issues are estimated in hours or days, Advanced Roadmaps will use time-based progress tracking.
- If issues are estimated in story points, point-based aggregation will be used.
- If you connect to boards and projects that have different plan units, Advanced Roadmaps will let you choose the estimation unit to use when you're creating the plan.
- If you leave your issues unestimated, progress will be calculated based on issue resolution, as well as the progress of child issues, if any.
"