I have created a plan, assigned Story Points and assigned Developers to issues. When I click 'auto-schedule', there are no changes made. Do I need to configure something else in each task? Do I need to assign a Sprint for each task?
My end goal is to be able to do this:
- specify a ranking for each task
- specify a developer for each task
- specify a fixed amount of hours or story points for each developer
- be able to auto set start and end dates based on the above
I have a setup in Excel that can do this quite easily but it seems to be impossible to do in Jira.
All of the resources online mention 'Advanced Roadmaps' but I can't see that anywhere in my Jira account.