Hi, Could anyone help me with moving a completed sprint, back to backlog in JIRA and how to navigate in JIRA to do so?
Hi @Bobin Johnson , you can Reopen a sprint which will return all issue from the sprint to the backlog. Note any issues defined in the completed sprint that were not completed that happen to be in a current active sprint will remain in the active sprint.
please see this article - Reopen Sprint
Thank you so much! this worked