Hi,
We are trying to use the auto scheduler in plans to plan out our asset creation for our kanban teams in a sequential manner to create a production plan and therefore a high-level roadmap.
All tasks are in Epics, and we can have two Epics running parallel, but not more.
But instead of scheduling sequential, it plans too many tasks in parallel. See picture below.

Here is what we tried:
- Assigned each task to individual persons
- Adjusted team capacities
- Entered target start dates based on start and end dates set in the plan settings
- Linked dependencies, but not overarching Epics (this would be too much work and defy the purpose to using auto scheduler in the first place)
Does anyone know if we are missing anything to make this work?