Hi.
I have tried a few tutorials and posts here, but unfortunately I cannot make it work.
I already have automation working to update Epic's 'Story Points' when a Story ('Story Done' only)
I want to to the same for Epic's and Initiatives. These are linked in our Jira project with a label of "Child issues".
Now I think about it, my first automation is flawed. I should only sum the Story Points when the Story status transitions to 'Story Done" not when the points change after it is done. Ooops.
EDIT: also I have another flaw, it needs to only sum up the story points of stories that are done. Now if a story is moved to done it will sum all the points regardless of the story status.