Hello Team,
I need some help with an automation. I have to check if delivery date for an issue is within the start date and end date of a sprint (sprint in which the issue is). For e.g, if the issue's delivery date is not within the start date and end date of the sprint (sprint in which the issue is), then the delivery date will be updated to NULL.
The issue is that I cannot check if the date 'is between' the sprint end date. I have only options greater than and less than. Any help on this please?

Also, if an issue is in a sprint but the sprint is not active yet, how will I build the automation please?
Thanks.